Isle of PalmsFriday, November 20
Isle of Palms opens a raised, wider path as Phase 2 of its flood barrier
The Morning Mount Pleasant team
If you walk or bike Waterway Boulevard on Isle of Palms, the path just got taller. The city held a 10 a.m. ribbon-cutting Thursday at Waterway Boulevard and Forest Trail for Phase 2 of its flood barrier project, which elevated and widened the pathway. Mayor Phillip Pounds said, "We hopefully have protected this thing up to about a 10-foot tide."
The barrier aims past the 2023 nor'easter's 9.86-foot tide
Sources: WCIV, Post and Courier
View as table
| Value | |
|---|---|
| Dec. 2023 nor'easter | 9.86 feet |
| Barrier goal (about) | 10 feet |
| Hurricane Hugo, 1989 | 12.52 feet |
The price tag grew. A $275,000 budget line item in 2018 to fix a neglected bike path became a $7 million, multi-phase project, and the December 2023 nor'easter added an extra foot of elevation. Engineers are still developing a plan for the third and final phase that accounts for nearby buildings and homes.
- Phase 1: berms leading into the golf course
- Phase 2: elevated, widened path, now open
- Phase 3: fills two gaps in the barrier
- Gap spots: 3607 to 3615 Waterway Blvd., Fire Station No. 2
The flood barrier project by the numbers
- 1.7 miles
- of drainage improvements on the island
- 8,850 feet
- of pathway improvements
- 29
- property owners gave permission and easements
- 650
- properties protected, worth about $1.2 billion combined
Source: Post and Courier
Sources: WCIV, Post and Courier, WCBD News 2